| Licence
Condition: |
Needed only if
supplying electricity to final customers |

|
Accede to the Trading and Settlement Code |
|
Name
of Form: |
Admission Application Form
|
|
Required
if: |
If wish to become a participant and
begin trading electricity under the Trading and
Settlement Code |
|
Available From: |
Download Application Form Here >>
This form is also available online at the CER web
site:
www.cer.ie
and the EirGrid website: www.eirgrid.ie
N.B new market arrangements for electricity
are currently being developed by the CER for implementation
by 19 February 2006
|
|
Submit To: |
By Registered Post:
Settlement System Administrator
ESB National Grid
27 Lower Fitzwilliam Street
Dublin 2
Or Fax to: + 353 (0)1 702 6040 |
|
| Application
Fee: |
- Payment of any amount under the Code shall be
made in accordance with Section 17 of the Code
- Require a €20,000 security cover
|
|
Accompanying
information required |
- Must fulfil the admission requirement of the
Code
- Must accede to the Framework Agreement
- Must provide the Settlement System Administrator
with the Standing Data required to commence trading
- The Settlement System Administrator will require
the Meter Registration System Operator (MRSO)
or Transmission System Operator (TSO) to confirm
in writing to the SSA that all of the metering
requirements of the applicant have been met.
|
|
When to submit: |
Must hold CER Supply Licence before submitting
application |
|
Average Length
of Time taken for the application to be processed: |
- Upon acceptance of the application of admission,
as soon as is reasonably practical
- A copy of the approved application, marked "Accept",
will be emailed or faxed to the applicant, and
also to Meter Registration System Operator (MRSO),
Transmission System Operator (TSO), and Commission
for Energy Regulation (CER)
- Following receipt by CER of a copy of the accepted
application, the applicant will be invited to
execute the Framework Agreement.
- If CER objects to the application, the application
shall be rejected.
|
|
Available Guidance: |
Agreed Procedure No. AP09 document - Market Entry
and Participant Registration, Guidance Notes
Further guidance can be obtained from the SSA Market
Support
|
|
FURTHER INFORMATION:
Current Bilateral Contracts Market
Ireland currently operates a day ahead
bilateral contract market pursuant to which generators
nominate to the transmission system operator (TSO), on
a day ahead basis, the schedule of energy they want to
produce and the prices they require. The market rules
are set out in the Trading and Settlement Code (Code).
A CHP plant is subject to central dispatch under the Grid
Code on the same basis as conventional units.
The TSO determines a merit order for
dispatch purposes on the basis of the schedules submitted
by generators. Initial commercial positions are based
on forecasts and therefore imbalances between projected
supply and demand often occur. The Settlement System Administrator
(SSA) calculates imbalances and market participants are
able to initially trade out imbalances amongst themselves.
Aggregate imbalances are then settled by the purchase
of "Top up" from and sale of "Spill" to ESB.
The holder of a Supply Licence or any
centrally dispatched plant must accede to and comply with
the Code. However, a non-centrally dispatched plant does
not have to accede to the Code unless it wishes to trade
electricity. Therefore, a CHP unit, which produces only
for its own use and does not "Spill" onto the system,
does not have to accede to the Code. The process for acceding
to the Code is by application to the TSO and the CER pursuant
to Agreed Procedure No. 9.
Since July 2003, CHP suppliers are required
to balance only 95% of their demand in their first year
of trading, allowing a 5% margin of error in recognition
of the difficulty of balancing a supplier's demand on
a certain date at a certain time. CHP generators are required
to balance 92% of the their rated capacity of sales to
CHP suppliers with its CHP tradable quantity, again recognising
a CHP generator's outage probability.
New Market Arrangements in Electricity
New Market Arrangements for Electricity
("MAE") are currently being developed by the CER and are
required to be implemented in Ireland on or before 19th
February 2006.
However, on 16th June 2004 the CER announced
that it would delay the implementation of the MAE for
a period of approximately 3-4 months to allow for the
consideration of changes to the MAE market design and
for the introduction of a new market implementation and
procurement process. This may therefore require an extension
of the implementation deadline. The high level principles
of the MAE include:
- A mandatory centralised pool market requiring all
electricity to be bought from and sold to the system
and market operator (SMO). This will mean that it will
no longer be possible for market participants to contract
to buy and sell physical electricity from each other.
They may only buy and sell electricity from the pool.
- Market participants may manage their exposure to volatility
in the pool price for electricity by entering into various
forms of hedging arrangements. At their simplest level,
these may be contracts for differences between the pool
price and an agreed strike price entered into by generators
and suppliers.
- The pool will be an energy-only spot market with no
payments for capacity. Generators who are not dispatched
due to constraints, or because their bids are above
the spot price, will not receive any payments in the
spot market. The spot market will be cleared and corresponding
dispatch schedules determined for half hour trading
intervals.
- The market clearing price for each generation node
will be the locational marginal price (LMP) at that
node. The nodes have not yet been specified but will
be designated by the CER. A load weighted average demand
price or Uniform Wholesale Spot Market Price (UWSMP)
will be calculated for all demand nodes.
- A regime of financial transmission rights will be
implemented which will enable generators to hedge differences
between the price at their generation node (i.e. their
LMP) and the load weighted average demand price (i.e.
the UWSMP).
The CER has recently published a decision in relation
to the treatment of CHP in the new market arrangements
for electricity (MAE). Key elements of this decision are
as follows:
- small-scale generators with an MEC of less than 100kVA
shall be exempt from the MAE Rules; generators with
an MEC of less than or equal to 5MVA will self-dispatch;
generators with an MEC greater than 5MVA must register
with the SMO as centrally controllable and may be dispatchable
if they satisfy the requirements of the Distribution/Grid
Code; and generators with an MEC of 30MVA or more must
be dispatchable;
- self-dispatched and centrally controllable generators
will be required to produce for the SMO a "best-efforts"
schedule comprising, at minimum, estimated plant output
per trading period from day-ahead up to gate closure;
- grid connected generators and generator sites with
an aggregate MEC greater than 5MVA will receive the
LMP at its node; distribution-connected generators with
a MEC less than or equal to 5MVA will receive the UWSMP;
and
- the MAE rules will not insulate generators from negative
pricing; therefore, if the spot price becomes negative,
generators exporting electricity directly to the pool
may be required to pay the negative spot price multiplied
by the volume of electricity that they are exporting.
|