| Licence
Condition: |
This Licence is
Mandatory. |

|
Planning Application Form |
|
Name
of Form |
Planning Application Form
|
|
Required
if: |
Seeking to construct a CHP Plant
(Pre-consultation should be held with the planning
authority on a case by case basis to determine whether
the proposed development requires planning permission,
and if so, whether an Environmental Impact Study
will be required). |
|
Available From: |
Planning Authority in whose jurisdiction the
site is located.
*
View the ICHPA Local Planning Authority List Here
>>
This list contains key contact details
for the 29 local councils in Ireland |
|
| Submit
To: |
Application is made to the Local Planning Authority
in whose jurisdiction the site is located. |
|
| Application
Fee: |
This Varies According to the proposed development |
|
Accompanying
information required |
All Planning Authorities have varying requirements.
In general, applications require the following:
- Contact details and the address of the land
or structure concerned;
- Legal interest of the applicant;
- Where the application relates to a building
or buildings, the gross floor space of any existing
building(s) and of the proposed works;
- Indicate if the development comprises or is
for the purpose of an activity in relation to
which an IPC/IPPC or waste licence is required;
- Indicate if the development consists of or comprises
the carrying out of works to a protected structure;
- Submission of a copy of the newspaper notice
published and the site notice erected on the land
or structure two weeks prior to submission of
the planning application;
- Six copies of a location map;
- A plan showing the position of a site notice
or notices affixed to the land or structure;
- Documents, particulars, plans, drawings and
maps, in metric scale, as required. Site or layout
plans must be of not less than 1:500 scale. Other
plans, elevations and sections must be of not
less than 1:200 scale.
In some cases an Environmental Impact Study may
be required, the applicant must consult the planning
authority to determine the requirement. |
|
When to submit: |
At the beginning of the approvals process. |
|
Average Length
of Time taken for the application to be processed: |
- Eight to sixteen weeks, depending on third party
submissions, or if accompanied by an Environmental
Impact Study.
- If appealed, An
Bord Pleanála has a statutory objective
to dispose of appeals within four months.
|
|
Available Guidance: |
Most local planning authorities have guidance
notes that accompany planning application forms.
In addition, applicants should contact the planning
authority and engage in pre-consultation to determine
whether planning permission is required, and if
so, what information will need to be submitted with
the planning application. |
|
Obtaining Planning Permission
The Planning
and Development Act (2000), Section 32, sets out a
general obligation for private developers to obtain planning
permission for development. The application is made to
the Planning Authority in whose jurisdiction the site
is located.
In some instances, for example where
a material change to the existing development will not
occur, planning permission may not be required. A further
example might be where a proposed CHP facility will replace
an existing boiler and no construction works are required.
Advice should be sought from the local
planning authority on a case-by-case basis. If permission
to proceed without planning permission is granted, official
Confirmation of Exemption must be obtained.
In all other circumstances, planning
permission is required by law.
Preparation of Planning Application
Article 22 of the Planning
and Development Regulations (2001), outlines the general
content of planning applications. Each County or City
has slightly different requirements. Copies of planning
application forms can be obtained from the relevant County
or City Council. Some example application forms are included
in Annex B.
Generally, a planning application requires
statement of, details on, and submission of:
- Contact details and the address of the land or
structure concerned;
- Legal interest of the applicant;
- Where the application relates to a building or
buildings, the gross floor space of any existing building(s)
and of the proposed works;
- Indication of whether the development comprises
or is for the purposes of an activity in relation
to which an IPC/IPPC or waste licence is required;
- Indication of whether the development consists
of or comprises the carrying out of works to a protected
structure;
- Submission of a copy of the newspaper notice published,
and the site notice erected on the land or structure,
two weeks prior to the submission of the planning
application;
- Six copies of a location map;
- a plan showing the position of a site notice or
notices affixed to the land or structure; and
- documents, particulars, plans, drawings and maps,
in metric scale, as required.
* This list is an indicative list only.
Refer
to Part 4 of the Planning and Development Regulations
2001, and to the relevant planning application form,
which can be obtained from your local
planning authority.
Site or layout plans must be of not less
than 1:500 scale. Other plans, elevations and sections
must be of not less than 1:200 scale.
Determination of whether an EIS is required

In some situations, an Environmental
Impact Statement (EIS) may be required for submission
with the planning application. The applicant should consult
directly with the local planning authority to determine
whether they require an EIS.
The planning authority will request an
EIS where it considers that the development is likely
to have ‘significant effects on the environment’.
The criteria for determining this are detailed in Schedule
7 of the 2001
Planning and Development Regulations.
The requirement for a formal Environmental
Impact Assessment (EIA) was introduced to European Union
Member States through Directive 85/337/EEC (as amended
by Directive 97/11/EC). This Directive was first transposed
into regulations in Ireland in 1990 and has undergone
several revisions as both the Directive and Irish law
have developed. The currently Applicable Irish Legislation
is the Planning
and Development Act (2000) and the Planning
and Development Regulations 2001.
As such, the planning authority may apply
environmental criteria to its planning considerations
under Section 43 (2) (a) of the Act and may specifically
refuse permission under Sections 256-257 (*) of the Act
notwithstanding any decision of the EPA. It is therefore
critical that, if an EIS is required that the design of
the facility parallels the completion of the EIS and that
the EIS underpins the planning application.
* Section 256 relates
to the amendment of the Environmental
Protection Agency Act, 1992 and Section 257 relates
to the Amendment
of the Waste Management Act, 1996
Following Lodgement of the Planning
Application
Upon lodgement of the planning application, the Planning
Authority will allow five weeks for the receipt of any
Third Party submissions or observations in relation to
the application (1). A planning
application that is accompanied by an EIS will be automatically
referred by the planning authority to the relevant ‘prescribed
bodies’ for assessment and comment
(2). Appeals in relation to submissions/observations
made outside this statutory five-week period, without
the appropriate fee or a copy of the receipt of objection
from the local planning authority, will be deemed invalid.
The Local Planning Authority may then
require the applicant, by notice in writing within eight
weeks of receipt of the planning application, to
(3):
- submit any further information (including any plans,
maps or drawings, or any information as to any estate
or interest in or right over land), which the authority
considers necessary to enable it to deal with the application;
or
- produce any evidence, which the authority may reasonably
require to verify any particulars or information given
in, or in relation to, the application.
If the additional information response
is determined by the planning authority to contain significant
additional data, including information in relation to
effects on the environment, it shall notify prescribed
bodies and objectors and require publication of a newspaper
notice to that effect.
Under Article 33 (3), a planning authority may request
clarification of responses in respect of the issues raised
in a request for additional information.
With the assistance of the original planning
application, and any further information requested, the
planning authority will then make a decision on whether
to grant or refuse permission for the proposed development.
This decision (Notification of Decision) must be handed
down within eight weeks of its request for further information
being complied with.
Upon submission of the planning application
to the local planning authority there are two possible
scenarios:
- Notification of Decision to grant or refuse permission
for the proposed CHP facility will be handed down and
will be accepted; or alternatively; or
- the Notification of Decision will be appealed, in
which case it will be referred to An
Bord Pleanála.
(1). Refer to the Article
28(2)(b) of the Planning
and Development Regulations, 2001.
(2). Refer to Part 3 of
the Planning
and Development Guidelines, 2001.
(3). Refer to Article
33 of the Planning
and Development Guidelines, 2001.
Upon Lodgement of Appeal with An Bord
Pleanála

If the planning authority’s decision
is appealed, (which can be done by either the first party
applicant or a third party person) the application will
be forwarded to An
Bord Pleanála.
The submission of an appeal to An
Bord Pleanála is in effect a completely new
application for planning approval. The decision of the
Board will over-ride any decisions issued by the local
planning authority.
Typically, an Inspector will be assigned
to the case, and will report back to the Board who will
then issue their decision on whether to permit or deny
the planning application. Oral hearings are sometimes
held to assist the Board in its understanding of particularly
complex cases or where significant national or local issues
are involved. The hearing is designed to allow further
necessary elaboration, discussion and examination of relevant
planning issues over and above the written appeal submissions.
Planning Application Process

Next Section

2. Authorisation to Construct or Reconstruct a
Generating Station (CER) >>
|