| Licence
Condition: |
This Licence
is Mandatory. |

|
Authorisation to Construct or Reconstruct a
Generating Station (CER) |
|
Name
of Form |
Commission for Energy Regulation (CER) Authorisation
to Construct or Reconstruct a Generating station
|
|
Required
if: |
Seeking permission to construct a
CHP Plant.
N.B This form can be submitted
jointly with the application for the Generation
Licence |
|
Available From: |
Commission
for Energy Regulation Website
Download the Application Form for this Licence Here
>>
Download CER Guidance Notes for this Licence Here
>>
These documents are available from the CER website:
www.cer.ie
Additional Information:
Application Licence:
http://www.cer.ie/CERDocs/Authorisation_Application_v3.1.doc
Guidance Notes: http://www.cer.ie/cerdocs/authorisation_guidelines_v6.doc
|
|
Submit To: |
Commission for Energy Regulation
Plaza House
Belgard Road
Tallaght
Dublin 24
Telephone: +353 (0)1 4000 800
email: info@cer.ie
|
|
| Application
Fee: |
Varies According to installed capacity
Less than 1 MW |
€32 |
1MW to <15MW |
€270 |
15MW to <50MW |
€995 |
50MW to <100MW |
€1995 |
100MW to <200MW |
€6635 |
200MW to <500MW |
€16590 |
500MW+ |
€19905 |
|
|
Accompanying
information required |
For All Plants:
- Environment Impact Statement (if applicable)
- Construction and commissioning programme
- Maps showing location of the CHP facility to
which the application applies
- Planning Permission or confirmation of planning
exemption from planning authority
- IPC Licence (Where Applicable)
- Water Extraction Licence (Where Applicable)
- Connection Offer (Where Applicable)
- Power Purchase Agreement (Where Applicable)
For Plants Greater than 5MW
- Statement of accounts for last 2 years
- Outline 5 year business plan in relation to
the application, including information on project
finance
For Plants less than or equal to 5MW in
size
- Short business plan; or
- Confirmation that the applicant has applied
for AER funding or has a PPA
|
|
When to submit: |
Upon receipt of planning permission or notification
of planning permission exemption |
|
Average Length
of Time taken for the application to be processed: |
- Application should be acknowledged in writing
within seven working days of CER's receipt of
the application form
- The applicant will be provided with a phone
number and a named contact for any enquires
- Application will be processed as rapidly as
possible
|
|
Available Guidance: |
CER Guidance Notes available here:
Download CER Guidance Notes Here >>
Also available online at www.cer.ie
|
|
FURTHER INFORMATION:
CER Authorisation to Construct or Reconstruct
Licence Overview
Before constructing a CHP Facility, authorisation
to proceed is required from the Commission for Energy
Regulation (CER). This Authorisation is the key administrative
permission required to construct a generation facility
(*Issued by the CER pursuant to section
16(1) of the 1999 Act.).
An Authorisation is obtained by application
to the CER. Commencement of construction of a generating
station without an Authorisation may result in a fine
up to €126,973.00 (Section
16(4) of the 1999 Act.). If the application
is refused, the applicant will be notified in writing
of the reasons for the refusal. A decision to refuse to
grant an Authorisation may be appealed
(4) The appeal procedure is set out in Part IV, sections
29 to 32 of the 1999 Act. An explanation of the appeal
procedure may also be found in paragraphs 46
to 47 of the Guidance Notes.
When Generating Capacity is Less than
or Equal to 5 megawatts:
The application and assessment procedure for an Authorisation
depends on the size of the proposed generating facility.
In order to minimise regulatory burdens on smaller market
participants, a streamlined process has been implemented
for applications from small-scale generators (less than
or equal to 5 megawatts)
(*CER Decision CER/03/061: "Modification
of the Commission's Procedures for Assessing Small-Scale
Licence Applications" dated 19 March 2003).
This streamlined process is as follows:
- Financial Assessment: Applicants must submit
details of directors and principal shareholders, a short
business plan and, if applicable, confirmation of the
existence of a power purchase agreement (whether or
not under AER);
- Technical Assessment: Applicants must submit
technical specifications of each unit, a connection
offer, planning permission, an environmental impact
statement (if applicable) and a construction and commissioning
programme.
- Fees: The fee for an application for a plant
less than 5 megawatts is €35.
When Generating Capacity is Greater
than 5 megawatts:
For plants greater than 5 megawatts, applicants must pay
an application fee and submit two copies of the following
documents with their applications:
- Financial Information: accounts for the
last two years, including a certificate that no material
change has occurred if more than three months have elapsed
since the end of the financial year (and accounts of
the parent company in the case of an SPV) (While it
will not routinely request or assess financial information
for applications of this size the CER reserves the right
to request its submission) . Applicants must also submit
a five-year business plan including annual forecasts
of costs, sales and revenues and financing.
- Environmental impact statement: if applicable.
- Construction and commissioning programme:
This must identify the major milestones in the project
development, from authorisation to completion.
- Map(s): sufficient to identify the location
of the generating station.
- Application Fee: fees vary according to
the installed capacity of the generating unit. The scale
of fees is set out above.
In addition, to assist the CER in assessing
applications in a timely manner, applicants are encouraged
(but not required) to provide the CER with two copies
of the following documentation (where applicable):
Public Procurement Obligations
A developer of a CHP plant may need to comply with the
formalities prescribed in EC Public Procurement Directives
in certain circumstances. In general, the Utilities Directive
(Directive
93/38/EEC, as amended by Directive
98/4/EC) applies to entities that hold authorisations
and/or licences, such as those necessary for a CHP plant,
and which are engaged in “relevant activities”
for the purposes of that Directive. Materially, such activities
are “the provision or operation of fixed networks
intended to provide a service to the public in connection
with the production, transport or distribution of electricity”
or “the supply of … electricity … to
such networks”.
In practice this means that a CHP plant
that intends to export into the grid falls under the Directive.
Furthermore, a CHP plant that intends to export to other
business enterprises, and where the means of export itself
forms part of a fixed network (for example, in an industrial
estate), might also fall under the formalities of the
Directive. In such instances, the formalities include
the requirement to advertise, by call for competition,
(tender notice) in the Official Journal of the European
Union (“OJEU”) and abiding by certain prescribed
procedures and time limits. In practice, time limits of
up to 77 days (This period may vary according to the circumstances
and according to which Directive and which procedure is
applicable) must be allowed to tenderers. Further periods
may be required to allow for the evaluation process. Failure
to abide by these formalities may result in awards of
monetary damages, injunction, declaration of voidness
or other remedies.
However, if the CHP plant is not intending
to supply electricity to the grid, or if it does not supply
electricity to other business enterprises as above, the
Utilities Directive will not be applicable. Furthermore,
the Utilities Directive does not apply if the financial
value of the procurement is below the financial thresholds
therein which, in general, are €5,923,624 for construction
contracts and €473,890 for goods and many services.
(In general, where Annex 1A of the Services
Directive or Annex XV1 A of the Utilities Directive apply
the only formality required is publication of an award
notice and other categories of services required to be
advertised if the financial threshold is exceeded.)
In general, public sector bodies will
be bound by the formalities of the Directives (but with
lower financial thresholds) in respect of procurement
of goods or certain services, as well as for construction
contracts if the Utilities Directive would not be applicable
to them in the relevant circumstances.
Next Section

OPERATION OF A CHP FACILITY >>
|