Connection to the
Electricity Grid |
 |
2.
Electricity Connection Agreement with TSO |
| Licence
Condition: |
This Licence
is Mandatory. |

|
Electricity Connection Agreement
with the TSO |
|
Name
of Form: |
Application for Connection to the
Electricity Transmission System Generators
|
|
Required
if: |
If a CHP facility is seeking
to connect to the transmission system. CHP
facility's seeking connection of less than
20MW size may wish to consider a connection
to the distribution system first. |
|
Available
From: |
Download the Application Form Here >>
Connection Offer Process - Guidance Notes
>>
This form is also available from: Eirgrid:
The Connection Offer Process |
|
| Submit
To: |
The Transmission System Operator (TSO) |
|
| Application
Fee: |
Fees vary according to the demand capacity
and generation capacity of the connection,
and whether any shallow works are required.
The schedule of fee rates is set out in
section 4.1 of the Guidance Notes.
View the Guidance Notes >>
|
|
Accompanying
information required |
|
|
When
to submit: |
Once you have received Budget Quotation
letter and associated estimated costs. |
|
Average
Length of Time taken for the application
to be processed: |
- TSO will make a connection offer within
70 days of receipt and acceptance of a
completed application form
- The offer will be valid for a period
of 70 business days from the date of issue
of the connection / quotation offer
|
|
Available
Guidance: |
Connection Offer Process - Guidance Notes
>>
Applicants have the facility
to explore connection options with ESB National
Grid (ESBNR) prior to submitting a connection
application. ESBNR offers a fee-based 'pre-feasibility
study' service designed to explore connection
opportunities without engaging in the Connection
Offer process if required.
|
|
|
|
FURTHER INFORMATION:
Transmission Connected CHP Facilities
An application for connection to the transmission
system is made by submitting an application
to the TSO, together with two signed confidentiality agreements,
together with two signed confidentiality
agreements and the first instalment of €7,000 of the
application fee. The second instalment will depend on the capacity
of the development and whether shallow connection works will
be involved. Details of application fees are set out in the
Process
for Connection to the Transmission System in Ireland issued
by ESB National Grid on the 16 June 2003.
The TSO will make a connection offer within
70 business days from receipt and acceptance of a completed
application, except in the case of complex connections. The
connection offer will comprise an offer letter which sets out
relevant charges and a standard form Connection
Agreement. The connection offer is valid for a period of
70 business days from the date of issue of the offer letter.
In order to accept a connection offer, the
generator will have to provide a signed copy of the Connection
Agreement, pay the first instalment of the Connection Charges
(equal to 10%) and provide a Connection Charges Bond for the
remainder of the Connection Charges, an MEC Capacity Bond can
be drawn down if the applicant city Bond equal to €10,000 per
MW of contracted capacity and possibly also an MIC Capacity
Bond. The MEC Capacity Bond can be drawn down if the applicant's
generation plant has not passed all capacity tests or the applicant
fails to submit a Capacity Certificate.
Payment of Connection and Use of System
Charges
Transmission connection charges in Ireland
are based on a shallow rather than a deep connection charging
policy. (CER
Direction CER/23/12) As an incentive for the ESB National
Grid to complete the necessary deep reinforcement works, generators
are granted "deemed firm" access to the system after
prescribed time periods, after which the generators will be
paid constraint payments if they are constrained off (i.e. the
site is given permission and access to export its entire generating
capacity to the network. If the network cannot take the full
amount, company will be paid a 'constraints payment'). CER Direction
CER/01/72: "Firm
and Non-Firm Access to the Transmission System"
CHP producers largely pay connection and use
of system charges on the basis of the predominant use being
made of networks. If a CHP producer's maximum import capacity
(MIC) exceeds its maximum export capacity (MEC), then connection
and capacity charges are levied on its MIC, on the same basis
as a final customer. CER Direction CER/03/237: "Network
Charges for Autoproducers and CHP Producers". If a
CHP producer's MEC exceeds its MIC, then connection and capacity
charges are levied on its MEC, on the same basis as a generator.
(Excluding costs required in relation to the provision of export
meters which must be paid for in full)
However, certain other transmission usage and
system charges are payable in respect of any net electricity
imports and all electrical exports, save that where a CHP Producer
connected to the distribution system has an MEC of less than
10 megawatts, that person shall not be charged generator related
Transmission Use of System Charges.
Draft CER Direction regarding Alignment of Connection
Offer Processes
The Commission for Energy Regulation (CER)
has recently proposed aligning the transmission and distribution
connection offer processes. Generators connected to the
distribution system do not pay distribution use of system
charges for exported energy, however these generators do
pay annual maintenance and operation charges associated
with the connecting asset. Key elements of the revised proposal
include:
-
subject to certain limited exceptions,
all connection offers shall be made within 70 business
days of receipt of a complete application and all connection
offers shall be valid for a period of 70 business days;
-
there shall be a single combined queuing
system for all generator connection applications in the
application process;
-
all transmission offers issued from 14th
May 2004 shall not be required to place a connection charges
bond and will be subject to a schedule of payment of 25%
of shallow connection costs on Offer Acceptance, 50% on
Consents Issue Date, and 25% on Connection Works completion;
-
all connection applicants shall pay application
fees and modification fees; · all connection applicants
shall be required to post a Capacity Bond of €10,000 per
megawatt as a condition precedent to offer acceptance;
-
a validity period of 36 months shall apply
from execution of the transmission connection agreement
to the Transmission Shallow Operational Date or execution
of the distribution connection agreement to the Final
Energisation date; and
-
transmission connected generators less
than or equal to 10 megawatts and distribution connected
generators shall post a Decommissioning and Reinstatement
Bond (D&R Bond) on Year 15 following commissioning of
the generation unit (or units) or two years prior to decommissioning,
whichever is the earlier. Transmission connected generators
above 10 megawatts shall post a D&R Bond on notification
of the decommissioning of the generation unit or units
as required by the Grid Code.
|