Electricity Connection Agreement
with the DSO |
|
Name
of Form: |
Application for Connection to the
Electricity Distribution System: Generators
|
|
Required
if: |
A CHP facility which exports
or imports electricity from the distribution
system must enter into a connection agreement
with the distribution system operator ("DSO"). |
|
Available
From: |
Download the Application Form Here >>
Download the ESB Guidance Notes Here >>
These documents are available from the
ESB website:
URL: http://www.esb.ie/esbnetworks/ |
|
| Submit
To: |
Electricity Supply Board (ESB)
Networks
Osprey House
Lower Grand Canal St,
Dublin 2
Tel: 01 6765831
Fax: 01 6615376
Email: esbnetworks@esb.ie
|
|
| Application
Fee: |
€100 where a site visit is required. |
|
Accompanying
information required |
- 2 Copies of site and location maps,
electrical single-line diagram of the
facility, and functional block diagrams
and generator details
- load or generator details
|
|
When
to submit: |
- After receipt of planning permission
(if required)
- ESB suggest that a planning study be
commissioned of the ESB (cost €635)
prior to submitting this application form.
The planning study will include a budget
quotation outlining connection options
and associated estimated costs.
|
|
Average Length of Time taken for the application
to be processed:
|
| Time Scale
/
Description |
From |
To |
|
| Quotation sent to customer |
Receipt of completed application |
18 weeks |
|
| Acceptance of Offer |
Period for which quote is valid |
3 months |
|
| Connection Works |
Acceptance of Offer |
9 months |
|
| Final Energisation |
Date of customer's notification/advice
of completion of Customer Connection
Works |
1 month |
|
| Typical Project Duration |
Receipt of completed application |
12 months |
|
|
Available
Guidance: |
Download the ESB Guidance Notes Here >>
Download the ESB's General Conditions for
Connection of Industrial and Commercial
Customers and Generators to the Distribution
System >>
These guidance notes are also available
from the following website:
http://www.esb.ie/esbnetworks |
|
FURTHER INFORMATION:
Distribution Connected CHP
Facilities
An application to the DSO which
includes: load or generator details; final address
details; an application fee of €100 (where a site
visit is required); site and location maps; electrical
line and functional block diagrams; and generator
details.
On receipt of the completed application,
a Quotation Letter and Connection
Agreement will be sent to the customer. The
connection offer will provide a costing for the
works to be undertaken by the DSO up to the connection
point. Connection works will be carried out in
accordance with the quotation letter on receipt
of:
- payment in full, or payment of the first instalment;
- signed Connection Agreement or Acceptance
of Offer Form; and
- completion of relevant documents if transfer
of the substation site to the ESB is required.
If an ESB planning study is sought
to assess the implications of a connection at
a particular point on the Distribution System,
a standard charge of €635 will be payable in advance
of a planning study or statement being prepared.
Some users may also request a capacity statement
giving information regarding circuit capacities,
present or projected power flows or loadings on
a part of the system. The standard fee for this
statement is €254.
Timescales for applications (subject
to wayleaves, planning permission and customer's
acceptance of offer) are outlined below:
Time
Scale Description |
From |
To |
Quotation sent to customer |
Receipt of completed application |
18 weeks |
|
Acceptance of Offer |
Period for which quote is valid |
3 months |
|
Connection Works |
Acceptance of Offer |
9 months |
|
Final Energisation |
Date of customer's notification / advice
of completion of Customer Connection Works |
1 month |
|
Typical Project Duration |
Receipt of completed applications |
12 months |
Customer connection works must
comply with the Distribution
Code and must be completed to specification
prior to commencement of ESB Connection Works
on the Customer's site.
Declaration of Fitness
for Service / G10 Form
The applicant will be responsible
for carrying out pre-commissioning and compliance
tests to ensure that the CHP facility meets appropriate
standards, and that competent personnel are operating
the equipment. This is mandatory.
A 'test results sheet' that provides
details on the generators relay calibration, operating
conditions, and functional operation must be submitted
to the Electricity Supply Board (ESB). The ESB
will review this information, and if satisfied
will issue the applicant with a Declaration of
Fitness for Service.
The test results sheet and associated
details on the conditions governing connection
to the distribution system can be obtained from
ESB.
Further
documentation is available from the ESB website
>>