   Construction of a CHP Facility Operation of a CHP Facility Connection to the Electricity Grid Electricity Supply & Trading Arrangements

Connection to the Electricity Grid

1. Electricity Connection Agreement with DSO

Licence Condition: This Licence is Mandatory.

ESB Networks

Electricity Connection Agreement with the DSO

Name of Form:

Application for Connection to the Electricity Distribution System: Generators

Required if:

A CHP facility which exports or imports electricity from the distribution system must enter into a connection agreement with the distribution system operator ("DSO").

Available From:

Download the Application Form Here >>

Download the ESB Guidance Notes Here >>

These documents are available from the ESB website:

URL: http://www.esb.ie/esbnetworks/

Submit To:

Electricity Supply Board (ESB)
Networks
Osprey House
Lower Grand Canal St,
Dublin 2

Tel: 01 6765831
Fax: 01 6615376
Email: esbnetworks@esb.ie

Application Fee:

€100 where a site visit is required.

Accompanying information required

  • 2 Copies of site and location maps, electrical single-line diagram of the facility, and functional block diagrams and generator details
  • load or generator details

When to submit:

  • After receipt of planning permission (if required)
  • ESB suggest that a planning study be commissioned of the ESB (cost €635) prior to submitting this application form. The planning study will include a budget quotation outlining connection options and associated estimated costs.


Average Length of Time taken for the application to be processed:


Time Scale /
Description

From

To

Quotation sent to customer

Receipt of completed application

18 weeks

Acceptance of Offer

Period for which quote is valid

3 months

Connection Works

Acceptance of Offer

9 months

Final Energisation

Date of customer's notification/advice of completion of Customer Connection Works

1 month

Typical Project Duration

Receipt of completed application

12 months


Available Guidance:

Download the ESB Guidance Notes Here >>

Download the ESB's General Conditions for Connection of Industrial and Commercial Customers and Generators to the Distribution System >>

These guidance notes are also available from the following website:

http://www.esb.ie/esbnetworks

FURTHER INFORMATION:

Distribution Connected CHP Facilities

An application to the DSO which includes: load or generator details; final address details; an application fee of €100 (where a site visit is required); site and location maps; electrical line and functional block diagrams; and generator details.

On receipt of the completed application, a Quotation Letter and Connection Agreement will be sent to the customer. The connection offer will provide a costing for the works to be undertaken by the DSO up to the connection point. Connection works will be carried out in accordance with the quotation letter on receipt of:

  • payment in full, or payment of the first instalment;
  • signed Connection Agreement or Acceptance of Offer Form; and
  • completion of relevant documents if transfer of the substation site to the ESB is required.

If an ESB planning study is sought to assess the implications of a connection at a particular point on the Distribution System, a standard charge of €635 will be payable in advance of a planning study or statement being prepared. Some users may also request a capacity statement giving information regarding circuit capacities, present or projected power flows or loadings on a part of the system. The standard fee for this statement is €254.

Timescales for applications (subject to wayleaves, planning permission and customer's acceptance of offer) are outlined below:

Time Scale Description

From

To

Quotation sent to customer

Receipt of completed application

18 weeks

Acceptance of Offer

Period for which quote is valid

3 months

Connection Works

Acceptance of Offer

9 months

Final Energisation

Date of customer's notification / advice of completion of Customer Connection Works

1 month

Typical Project Duration

Receipt of completed applications

12 months

 

Customer connection works must comply with the Distribution Code and must be completed to specification prior to commencement of ESB Connection Works on the Customer's site.

Declaration of Fitness for Service / G10 Form

The applicant will be responsible for carrying out pre-commissioning and compliance tests to ensure that the CHP facility meets appropriate standards, and that competent personnel are operating the equipment. This is mandatory.

A 'test results sheet' that provides details on the generators relay calibration, operating conditions, and functional operation must be submitted to the Electricity Supply Board (ESB). The ESB will review this information, and if satisfied will issue the applicant with a Declaration of Fitness for Service.

The test results sheet and associated details on the conditions governing connection to the distribution system can be obtained from ESB.

Further documentation is available from the ESB website >>

 

Next Section



ELECTRICITY CONNECTION AGREEMENT WITH TSO >>

 

Construction of a CHP Facility Operation of a CHP Facility Connection to the Electricity Grid Electricity Supply and Trading Arrangements

 





This Legislative Map is based on material from a report by Arthur Cox Solicitors and ERM Environmental Resources Management Ireland Limited an "Evaluation of the Existing Legislation and Regulation affecting new CHP facility installation in Ireland" commissioned by Sustainable Energy Ireland.

Online CHP Evaluation Tool and Payback Calculator.  Irish CHP Association.  Supported by Sustainable Energy Ireland

Are you Considering a CHP Project?

Online CHP Evaluation Tool

The Irish CHP Association's Online Evaluation Tool is very simple to use and will give a reasonable indication of the feasibility (and payback time) of a CHP solution based on basic information about your current site energy consumption, costs, and site operating hours. Click here to begin >>

 

 

 

 



 

 

 

 

 

 


 

Questions/Comments? | Irish CHP Association Contact Information | Links

© Irish CHP Association. Last Updated: Fri 13 May 2005.